Newburyport Boardwalk Construction This Winter: Changes to Your Walk

October 29, 2026

When engineers pulled up deck boards on the Newburyport boardwalk in 2025, they found the supports in good condition. About 90 percent of the stringers and other supports underneath were in satisfactory shape, according to the city's project page. The problem was on top. Boards were splintering and rotting, and screws had lost their grip.

That one finding explains most of what you'll see along the Merrimack between now and spring. The city chose a partial rebuild instead of a full replacement. It costs less and fits inside one off-season, so the boardwalk should be back to normal before the summer boats arrive.

Twenty-five years of weather, mostly on the surface

The structure's official name is the Peter J. Matthews Memorial Boardwalk. It was built in the late 1970s and extended and redecked in 2002. The city calls it one of its primary civic spaces, used heavily by boaters, visitors and residents. Over the past 25 years, enough boards have weathered to create what the city calls increasing trip hazards.

The city's marine engineering consultant, GEI, pulled up boards in about half a dozen spots to look underneath. Its findings showed what had gone wrong. At some point, loose areas had been fastened down with 10-inch screws. The preservatives in the pressure-treated stringers corroded the threads on those screws, so they could no longer hold, and boards started lifting. GEI estimated that about 60 percent of the boardwalk needed new decking.

If parts of the walk felt patched together last fall, they were. The project page records the stopgap work:

  1. October 2025. BTT Marine Construction pre-drilled and installed about 200 new coated, longer screws to hold down loose boards. The city said the contractor would also swap a handful of the worst boards for pressure-treated pine.
  2. November 2025. Some spans were too long for pine boards to work, so the contractor ordered 3x8 oak hardwood deck boards for those sections.
  3. Fall 2025. The Newburyport Waterfront Trust paid for an experienced contractor to refasten a number of raised boards.

The city described those fixes as short-term safety measures while it planned the full rehabilitation.

Why composite boards, and why only part of the walk

Because the supports were mostly sound, the city could choose a partial rebuild and then pick a decking material. GEI's February 2026 presentation compared the options, and each one was ruled out for a concrete reason.

Option What the February 2026 project presentation found
Tropical hardwood About $225,000 more than composite, with longer import lead times and concerns about quality control and sustainability
Pressure-treated pine Cheaper, but splits and checks over time, needs replacing sooner, and raised chemical concerns
Precast or cast-in-place concrete Costlier, and judged not appropriate for Newburyport's boardwalk
Full reconstruction About $3 million, over $1 million more than the partial approach, and it would take more months and could cut into boating season
Partial reconstruction with composite decking The recommended approach

Sound Ipe decking stays. The same presentation says the existing Ipe that is still in good condition should last another 15 to 20 years. Once the work is done, the boardwalk will be a mix of the existing tropical hardwood and new composite boards.

In his September 14, 2026 update, Mayor Sean Reardon put the scope at about 70 to 75 percent of the boardwalk. That includes rebuilding the structure under those sections and installing new composite decking. GEI estimated that 60 percent needed new boards, so the rebuild goes somewhat beyond that figure, with an improved substructure under the new sections.

Who is paying

Most of the money comes from the state. On January 8, 2026, the Massachusetts Seaport Economic Council approved a $1,492,500 grant for the project. The grant required a local match of at least 20 percent. The city's announcement of the grant names the council's FY26 grant program as the source.

The February presentation lists the full funding:

  • Massachusetts Seaport Economic Council: $1,492,500
  • Community Preservation Act funds: $285,000
  • Newburyport Waterfront Trust: $50,000
  • Total: $1,827,500

The mayor's September update said the city expected to award the contract while keeping a healthy contingency within the grant-funded budget. Five general contractors submitted bids on September 10.

The calendar is set by the boats

Timing drives the whole plan. On the city's project page, the January update says construction has to happen during the fall and winter off-season to avoid significant disruption to boating season and to public use of the boardwalk in warm weather.

As of the September 14 update, the schedule was a preconstruction meeting in late September and construction starting in mid-October, after the waterfront floats come out. Work would continue through the winter, with completion expected in spring 2027. The February presentation gives a similar window: about six months of construction from October 2026 to April 2027, then a May 2027 punch list to finish everything before boating season and high summer use. The project page still says summer 2027 in its earlier wording. The newer target is spring, and like any construction date that runs through a coastal winter, it is a target, not a promise.

The city hasn't published a phasing plan or a list of which sections close when. Its September update is the latest public word on the project, and the Mayor's Updates page is the place to watch for the next one.

There is a precedent for getting around the work. When GEI inspected the boardwalk on August 13, 2025, crews fenced off about five feet at a time, starting at the Harbormaster's end on the east and moving toward the embayment. The city said people could go around on the waterfront park's shared-use path. A months-long rebuild is a much bigger job than a one-day inspection, but the path that runs alongside the boardwalk through the park is the obvious way around if sections close. The Waterfront Trust says Market Landing Park, the boardwalk and its other property are open for public use. That is a general statement, not a promise about construction-period access.

The waterfront that keeps going this winter

With the boardwalk under construction, the businesses and venues around it keep the waterfront busy. Each lists its own hours:

  • Custom House Maritime Museum, 25 Water Street. Its posted schedule is 10 a.m. to 5 p.m. Tuesday through Saturday and noon to 5 p.m. Sunday. Those are labeled summer hours, running Memorial Day through October, so check the site for the winter schedule before you go.
  • Firehouse Center for the Arts, 1 Market Square. The box office is open noon to 5 p.m. Tuesday through Saturday. Its events calendar lists shows through November 2026.
  • Sea Level Oyster Bar, 1 Market Square. Open 11:30 a.m. to 9 p.m. Sunday through Thursday and until 10 p.m. Friday and Saturday.
  • Michael's Harborside, 1 Tournament Wharf. Open 11:30 a.m. to 9 p.m. Sunday through Thursday and until 10 p.m. Friday and Saturday.
  • Tuscan Sea Grill & Bar, 38R Merrimac Street. Open 11 a.m. to 9 p.m. Sunday through Wednesday and until 10 p.m. Thursday through Saturday. Its deck is enclosed for the colder months.
  • The Poynt, 31 Water Street. Dinner runs 4 to 9 p.m. Tuesday through Thursday, 4 to 10 p.m. Friday and Saturday, and 3:30 to 7 p.m. Sunday. It also serves lunch on Saturday from 11:30 a.m. to 4 p.m. and brunch on Sunday from 10 a.m. to 3 p.m. The restaurant says hours can change on holidays and in the off-season and suggests calling ahead.

All six are on the waterfront or on the streets running into it, so a winter walk along the river this year can still end at a table or a gallery even if part of the boardwalk is fenced off. By the May punch list, most of the boardwalk will have a rebuilt structure and new boards, and the Ipe still in good shape will stay in place for another 15 to 20 years.

I'm watching the boardwalk work like everyone else, along with how changes on the waterfront shape the market around it. If you'd like a local read on what's happening near the river, or anywhere else in town, Jamie Frontiero is always happy to talk it through. Let's Connect.