October 29, 2026
When engineers pulled up deck boards on the Newburyport boardwalk in 2025, they found the supports in good condition. About 90 percent of the stringers and other supports underneath were in satisfactory shape, according to the city's project page. The problem was on top. Boards were splintering and rotting, and screws had lost their grip.
That one finding explains most of what you'll see along the Merrimack between now and spring. The city chose a partial rebuild instead of a full replacement. It costs less and fits inside one off-season, so the boardwalk should be back to normal before the summer boats arrive.
The structure's official name is the Peter J. Matthews Memorial Boardwalk. It was built in the late 1970s and extended and redecked in 2002. The city calls it one of its primary civic spaces, used heavily by boaters, visitors and residents. Over the past 25 years, enough boards have weathered to create what the city calls increasing trip hazards.
The city's marine engineering consultant, GEI, pulled up boards in about half a dozen spots to look underneath. Its findings showed what had gone wrong. At some point, loose areas had been fastened down with 10-inch screws. The preservatives in the pressure-treated stringers corroded the threads on those screws, so they could no longer hold, and boards started lifting. GEI estimated that about 60 percent of the boardwalk needed new decking.
If parts of the walk felt patched together last fall, they were. The project page records the stopgap work:
The city described those fixes as short-term safety measures while it planned the full rehabilitation.
Because the supports were mostly sound, the city could choose a partial rebuild and then pick a decking material. GEI's February 2026 presentation compared the options, and each one was ruled out for a concrete reason.
| Option | What the February 2026 project presentation found |
|---|---|
| Tropical hardwood | About $225,000 more than composite, with longer import lead times and concerns about quality control and sustainability |
| Pressure-treated pine | Cheaper, but splits and checks over time, needs replacing sooner, and raised chemical concerns |
| Precast or cast-in-place concrete | Costlier, and judged not appropriate for Newburyport's boardwalk |
| Full reconstruction | About $3 million, over $1 million more than the partial approach, and it would take more months and could cut into boating season |
| Partial reconstruction with composite decking | The recommended approach |
Sound Ipe decking stays. The same presentation says the existing Ipe that is still in good condition should last another 15 to 20 years. Once the work is done, the boardwalk will be a mix of the existing tropical hardwood and new composite boards.
In his September 14, 2026 update, Mayor Sean Reardon put the scope at about 70 to 75 percent of the boardwalk. That includes rebuilding the structure under those sections and installing new composite decking. GEI estimated that 60 percent needed new boards, so the rebuild goes somewhat beyond that figure, with an improved substructure under the new sections.
Most of the money comes from the state. On January 8, 2026, the Massachusetts Seaport Economic Council approved a $1,492,500 grant for the project. The grant required a local match of at least 20 percent. The city's announcement of the grant names the council's FY26 grant program as the source.
The February presentation lists the full funding:
The mayor's September update said the city expected to award the contract while keeping a healthy contingency within the grant-funded budget. Five general contractors submitted bids on September 10.
Timing drives the whole plan. On the city's project page, the January update says construction has to happen during the fall and winter off-season to avoid significant disruption to boating season and to public use of the boardwalk in warm weather.
As of the September 14 update, the schedule was a preconstruction meeting in late September and construction starting in mid-October, after the waterfront floats come out. Work would continue through the winter, with completion expected in spring 2027. The February presentation gives a similar window: about six months of construction from October 2026 to April 2027, then a May 2027 punch list to finish everything before boating season and high summer use. The project page still says summer 2027 in its earlier wording. The newer target is spring, and like any construction date that runs through a coastal winter, it is a target, not a promise.
The city hasn't published a phasing plan or a list of which sections close when. Its September update is the latest public word on the project, and the Mayor's Updates page is the place to watch for the next one.
There is a precedent for getting around the work. When GEI inspected the boardwalk on August 13, 2025, crews fenced off about five feet at a time, starting at the Harbormaster's end on the east and moving toward the embayment. The city said people could go around on the waterfront park's shared-use path. A months-long rebuild is a much bigger job than a one-day inspection, but the path that runs alongside the boardwalk through the park is the obvious way around if sections close. The Waterfront Trust says Market Landing Park, the boardwalk and its other property are open for public use. That is a general statement, not a promise about construction-period access.
With the boardwalk under construction, the businesses and venues around it keep the waterfront busy. Each lists its own hours:
All six are on the waterfront or on the streets running into it, so a winter walk along the river this year can still end at a table or a gallery even if part of the boardwalk is fenced off. By the May punch list, most of the boardwalk will have a rebuilt structure and new boards, and the Ipe still in good shape will stay in place for another 15 to 20 years.
I'm watching the boardwalk work like everyone else, along with how changes on the waterfront shape the market around it. If you'd like a local read on what's happening near the river, or anywhere else in town, Jamie Frontiero is always happy to talk it through. Let's Connect.